Paris based junior, Maurel et Prom (M&P), has pushed up its natural gas production in Tanzania by ~20Million standard cubic feet of gas per day (20MMscf/d), in the last nine months, averaging 130MMscf/d gross as of October 2026.
The increase came from two new wells MB-5 and MS-2, drilled in the first half of the year. The duo have shown the promise of ramping up the combined production potential of existing wells to nearly 200MMscf/d.
M&P said that a third well in the same asset, the Mnazi Bay field, made a discovery of natural gas volumes, estimated at approximately 200Billion cubic feet (Bcf) gross, or 120Bcf working interest for the company.
The Kasa-1X exploration well, drilling of which began in June 2026, is Tanzania’s first discovery in 10 years. “Drilled from onshore, the well reached a target located 4.5 kilometres offshore, beneath 400 metres of water”, M& P said in a statement.
“The initial penetration, which established the discovery, was immediately followed by the drilling of a side-track intersecting 588 metres of reservoir”.
First production is envisaged as early as November 2026, with expected gross production potential of 50MMscf/d. Processing facilities have been successfully tested at a capacity of 150MMscf/d.